# Wet-Leased Aircraft Induction Checklist for Airlines
- URL: https://www.acmiworld.com/wet-lease-aircraft-entry-into-service-checklist/
- Published: 2026-11-12T17:47:21.000Z
- Updated: 2026-11-12T17:47:21.000Z
- Description: A post-signature induction checklist for a wet-leased aircraft: documents, operations interface, crew, maintenance, insurance, airports, and release to service.
- Author: ACMI World
- Tags: ACMI Leasing

A signed ACMI or wet-lease contract is not the same as an aircraft that is ready for the first commercial sector. Induction, or entry into service, is the work after signature: documents, operational interfaces, crew, maintenance, insurance evidence, airport set-up, and a release to service that both parties can stand behind. This page is a practical checklist for airline operations and continuing-airworthiness teams. It is not a second "what is ACMI" explainer, and it is not a substitute for the lessor's procedures or the lessee's operations manual.

The contracting path that leads to this checklist is covered in [how to arrange an ACMI wet lease](https://www.acmiworld.com/how-to-arrange-an-acmi-wet-lease/). For clause issues that should already have been closed, use [ACMI contract clauses airlines should negotiate](https://www.acmiworld.com/acmi-contract-clauses-airlines-should-negotiate/). For the legal structure, use [wet lease versus dry lease](https://www.acmiworld.com/wet-lease-vs-dry-lease-explained-key-differences-for-aircraft-operators/). Insurance evidence is covered in [ACMI wet-lease insurance: hull, liability and war risk](https://www.acmiworld.com/acmi-wet-lease-insurance-hull-liability-war-risk/). Where a third-country aircraft is involved, keep [EASA and EU third-country wet-lease approvals](https://www.acmiworld.com/easa-eu-third-country-wet-lease-approvals/) in the same pack.

![Passenger aircraft on approach after a wet-leased aircraft has been released to service](https://storage.ghost.io/c/72/dc/72dcdb97-1931-4dfa-9858-c290b5d29ba8/content/images/2026/11/pexels-1089306.jpg)

Photo via [Pexels](https://www.pexels.com/?ref=acmiworld.com)

## Documents and records to have in hand

Before the aircraft is treated as inducted, the lessee should have current copies, or controlled access, to the items the contract and the competent authority require. A typical pack includes:

- The signed lease, including the operations, insurance, and maintenance schedules, and any side letters that affect the first sector.
- The lessor's air operator certificate and operations specifications, and evidence that the aircraft is on that certificate for the intended operation.
- Certificates of registration and airworthiness, noise and radio certificates as applicable, and the current insurance certificates that match the contract.
- The technical log, status of airworthiness directives and service bulletins, a current maintenance forecast, and a record of deferred defects that the parties have accepted.
- Weight and balance, the configuration list (seats, galleys, cargo systems, emergency equipment), and any MEL or CDL items that will be open at arrival.
- Approval evidence from the lessee's competent authority where a wet-lease approval is required, including any conditions attached to that approval.

If a document is "on the way," it is not inducted. Build a single tracker with an owner, a due date, and a place to store the file. Do not split the pack across email threads.

## Operations interface between lessor and lessee

On a wet lease the lessor remains the operator, but the lessee still has a schedule, a commercial product, and usually a ground organisation at the base. The interface should be written down before the first sector:

- Who issues the flight plan, the load sheet, and the release, and in whose operations control centre the flight is watched.
- How delays, diversions, and irregular operations are communicated to the lessee's customer-service and network teams, and in what time standard.
- Cabin product standards, if the lessee's brand is on the aircraft, including catering, uniforms, and what the lessor's cabin crew will and will not do.
- Dangerous goods, PRM, and disruption procedures, so the two manuals are not in conflict at the gate.
- Language, reporting forms, and a named 24-hour contact on each side.

A table in the operations schedule of the lease is more useful than a kick-off call that nobody minutes. Write that table in the same document the crews and the ground teams will actually use, and keep a dated copy in the induction pack so a late change to the reporting line does not live only in a chat history. If the product on sale does not match what the lessor can legally or practically fly, fix that before tickets go out, not at induction.

## Crew, training, and base set-up

Confirm that the named or rostered crew are qualified on the type and current for the routes and the airports in the programme, including any special approvals the sectors require. Simulator, line training, and airport qualification slots are a frequent reason a start date slips after the contract is signed. The lessee cannot crew the aircraft itself on a wet lease, but it can still delay the programme by changing the network after the lessor has already rostered a different pattern.

At the base, confirm parking, handling, fuel, catering, de-icing where relevant, spare parts arrangements, and access for the lessor's engineers. Hotel and report-time plans for the crew should be agreed, not assumed. If the aircraft will wear the lessee's livery, treat paint or decal time as part of induction, including any flight that is only a positioning or a proving sector.

## Maintenance status and continuing airworthiness

The lessor remains responsible for continuing airworthiness on a typical wet lease, but the lessee still needs a clear picture of the aircraft it is putting into a schedule. Review the maintenance forecast against the first weeks of flying, agree how defects will be reported into the lessee's irregular-operations process, and agree who can defer what, and at which station the next check can be performed. Components with a short remaining life should be visible in the pack, not discovered after a cancellation.

If a substitute aircraft is allowed under the contract, induction standards should apply to the substitute, not only to the tail that was named in the annex on signing day.

## Insurance, airports, and the release to first commercial flight

Insurance certificates should be current, should identify the aircraft, and should show the additional insureds and limits the contract requires, including war risk if the programme needs it. If an approval authority asked for insurance evidence, the copy in the induction pack should be the same copy, not an earlier draft.

Airports, slots, and traffic-right notices should already have been started in the arrangement phase. At induction, confirm that they are actually in place for the first sectors, including handling contracts and any local permission the aircraft or the operator still needs.

Only then should the parties issue a joint release that the aircraft may fly the first commercial sector. A positioning flight is not, by itself, a commercial release. If something in the pack is outstanding, the honest action is to delay the first revenue sector, not to hope it arrives mid-route.

Build a short proving plan if the base, the livery, or the cabin product is new to the lessor's crew. A proving or positioning sector can surface load-sheet, catering, and ground-handling gaps that would be expensive on the first revenue flight. Record what was tested and what remains open, and do not treat a successful positioning flight as automatic permission to sell the next sector if an approval condition or a document is still outstanding.

After the first commercial sector, hold a short wash-up: defects raised, communication delays, certificate or approval conditions that were easy to miss, and any substitute-aircraft rules that were almost used. Induction is finished when the first sector has been released and those early items have been closed or formally accepted. It is not finished merely because the aircraft has arrived on the ramp.

Keep passengers and cargo out of an unreleased aircraft. Marketing, airport display screens, and a published timetable can create pressure to operate while a certificate or a condition is still open. The operations lead on the lessee side should have the authority to hold the first sector, and that authority should be agreed with commercial teams before induction week, not argued at the gate.

## FAQ

### When does induction start?

Document collection and base planning should start as soon as the path to signature is clear, not on the day the aircraft arrives. Formal entry into service is the point at which the pack, the interface, and the approvals are complete and the first commercial sector is released.

### Who owns the checklist on a wet lease?

Both parties. The lessor owns the aircraft, the crew, and continuing airworthiness. The lessee owns its schedule, its approvals, and its ground product. A single tracker with named owners on each side is the practical way to hold that split.

### What if a document or approval is late?

Do not treat the aircraft as inducted. Reset the first commercial sector and, if the contract requires it, use the delay or termination mechanics that were already agreed. Do not invent a workaround that conflicts with the approval.

### Is a damp lease inducted the same way?

Many of the aircraft and approval items are the same, but crew supply is different, so the training and cabin-interface items change. Use the [damp lease versus wet lease versus ACMI](https://www.acmiworld.com/damp-lease-vs-wet-lease-vs-acmi-for-airlines/) article to keep the structure straight, then adapt the crew parts of this list.

### Where can we find the aircraft or list one that is ready to induct?

Use the marketplace, a wanted post, or a listing, and do not skip the induction pack once a contract is in view.

## After the contract, finish induction before the first sector

If you are about to take or place a wet-leased aircraft, use this checklist alongside the contract schedules. If you are still searching for capacity, post the requirement or list the aircraft first, then plan induction against a real start date.